Timeline and Prequalification
During the building period, we expect to employ up to 1,500 dedicated construction workers who share our commitment to excellence, innovation, and meticulous craftsmanship.
We are reaching out to skilled subcontractors like yourself to join us on this extraordinary journey, to lend your expertise and become an integral part of this historic venture.
Procurement Timeline
- Bid packages
- Core & Shell – July/August 2024
- Architectural Interiors – September 2024
- MEP – October/December 2024
- Remaining Site Work – August 2024
- Construction started: April 2024
- Anticipated construction completion: 2026
Prequalification
To be eligible to receive project documentation about the construction of the EPIC Center:
- Complete a Non-Disclosure Agreement (NDA): We value your trust and aim to foster a transparent yet confidential relationship. By completing the NDA, you commit to upholding the integrity of the project’s sensitive information. Complete the Non-Disclosure Agreement Here.
- Complete the Prequalification Form: Complete the prequalification on Hoffman’s Trade Partner page. Your completion of the prequalification form helps us understand your skills, capabilities, and capacity to contribute effectively to this ambitious project.