Fast, Complex Fab Construction in the Middle of an Operational Facility
Fab D1X Mod 1
Hoffman built this prototype microchip fabrication plant — one of the largest construction projects in Oregon history — on a crowded manufacturing campus that is home to some of the client’s most valuable processes. The work required complex and sensitive tie-ins to the operational facility.
The 1,300,000 SF microchip manufacturing plant features 240,000 SF of cleanroom space, a process utility building, a boiler-chiller plant, and a fab support building with labs and other facilities. A general purpose building adds a cafeteria and other office/support space for people working in the fab.
The project used 180,000 CY of concrete and 12,000 tons of structural steel. It required the use of one of the largest cranes in the world, a 2,600-ton Lampson crane. The fab was completed in 14 months.